Project Process
Option Period (2-4 years)
Landowners can continue the current use of the property (e.g. farming, grazing, etc.). Clean Grid will conduct studies, complete the interconnection process, and negotiate a power purchase agreement (PPA), among other development activities.
Construction Period (~6-12 months)
Landowners cease use of the leased property. Clean Grid will require full use of the leased property for the construction of the project.
Operations Period (~25 years)
Landowners cease use of the leased property. Clean Grid will require full use of the leased property for the operations of the solar farm.
Decommissioning Period (~6-12 months)
Clean Grid will remove all project infrastructure and restore the land to preconstruction conditions.